Quick Answer

Before a foundation is poured, the inspector checks that the footings and slab match the approved plans: the size and depth of the excavation, the soil at the bottom, the reinforcing steel and its supports, the forms and anything that will be buried in concrete, such as plumbing, sleeves and the vapor barrier. Do not pour until that inspection is signed off.

Which Inspections Happen Before Concrete?

Most departments inspect the footings before they are poured, then the plumbing under the slab, then the slab itself before concrete. The names and the order vary by city and county, so ask your building department for its list when the permit is issued.

What Does the Inspector Look At?

Location: The foundation sits where the site plan and setbacks say it should. Some departments require a survey of the forms.

Footing size and depth: Width and depth match the plans and reach undisturbed soil below the frost line.

The bottom of the trench: Clean, firm and free of loose soil, mud, water and debris.

Reinforcing steel: The bar size, spacing and overlap match the plans, and the steel is held up on supports, not lying on the dirt.

Forms: Braced, level and built to the right dimensions.

Under slab plumbing: Installed, tested and inspected before it is covered.

Vapor barrier and base: Gravel base in place, with the vapor barrier lapped at the seams and sealed around pipes.

Anchors and grounding: Anchor bolts and hold downs are on site with their layout marked, and the grounding connection to the steel is in place where required.

Why Do Foundations Fail Inspection?

Common reasons include steel resting on the ground, water or mud in the trench, steel that does not match the plans, a torn or missing vapor barrier and no approved plans on site for the inspector to read. Each one is cheap to fix before the pour and expensive after it.

What Should I Do the Day Before the Inspection?

Walk the foundation with the approved plans in hand. Measure the footings and the steel and take photos with a tape measure in the frame. Check the weather. Confirm the inspection has passed before you order concrete, and keep the signed approval with your records.

Common Questions

Can I Pour if the Inspector Does Not Show Up?

No. Pouring without approval can mean cutting out concrete at your cost. Call the department, reschedule and move the concrete order.

What if It Rains Before the Pour?

Standing water and mud have to be removed and the trench bottom restored. Some inspectors will want to look again before you pour.

Who Schedules the Foundation Inspection?

The permit holder does, which is the general contractor or you if you are acting as your own.

Walk Every Inspection With a Checklist

Formwork has a checklist for each inspection and shows what a miss typically costs to fix.

See Formwork

Newsletter

Get One Field Note a Week

One clear answer to a real building or investing question, every week. Unsubscribe anytime. See our Privacy Policy.

EnrollApply