Quick Answer
Put every bid into one sheet with the same line items, then fill the gaps until each bid covers the same scope. Compare what is included, excluded and allowed for before you compare price. The lowest number is often the bid that left something out.
Why Can I Not Just Compare the Totals?
Two bids for the same trade rarely price the same work. One includes materials and haul off, another does not. One assumes a cheaper grade of material. Until the bids cover the same scope, the totals tell you very little.
How Do I Level Bids Step by Step?
1. Send the same package: Give every bidder the same plans, the same written scope and the same deadline.
2. Build one sheet: List the line items down the side and the bidders across the top.
3. Mark each line: Note whether each bidder included it, excluded it or carried an allowance.
4. Fill the gaps: Ask each bidder to price what they left out.
5. Even out allowances: Set the same allowance and the same quantities for everyone.
6. Compare the leveled totals: Now the numbers describe the same job.
7. Check the bidder: Confirm license, insurance, references, start date and payment terms.
What Should I Watch For in a Bid?
Low allowances: A small allowance makes a bid look cheap until you pick real products.
Work by others: Those words move cost onto you or another trade.
Different quantities: Compare square feet, linear feet and counts against the plans.
Missing cleanup and haul off: Someone has to pay for it.
Large payment up front: Tie payments to finished work instead.
What Do I Do With a Bid That Is Far Lower?
Ask what is missing before you celebrate. Walk through your sheet with that bidder line by line. Do not share another bidder's price. Choose on complete scope, proof of past work and whether they can meet your schedule, then on price.
Common Questions
How Many Bids Should I Get for Each Trade?
Aim for 3. That is enough to see the range and to spot a number that is out of line.
Should I Always Take the Lowest Bid?
No. Take the lowest complete bid from a subcontractor who is licensed, insured and able to start when you need them.
What Is an Allowance in a Bid?
It is a placeholder amount for something not chosen yet, such as tile or fixtures. If your choice costs more than the allowance, you pay the difference.